Elliott Group Brochure ROI 052022 T.2 - Flipbook - Page 62
Elliott Group | A Tradition in Construction
Cavan | Dublin | Cork | London | Birmingham
CF Unit Beaumount | Live Project
Beaumont Hospital
Beaumont Hospital have developed a new
dedicated three storey, 20 Bed in-patient Cystic
Fibrosis Unit which will form part of the National
Clinical Care Programme for Cystic Fibrosis
(NCPCF), providing specialised care tailored to
the needs of cystic 昀椀brosis patients. The Scott
Tallon Walker led design team proposal is based
on providing single occupancy high dependency
PPVL bedroom accommodation. These rooms
will be equipped and supported by state-of-theart treatment facilities that will integrate with
the Main Hospital to ensure seamless access to
comprehensive medical care’.
KEY FEATURES
20 Bed in-patient Cystic Fibrosis Unit
Isolation Rooms
The 昀氀oor area consists of 553.05m2 on the lower
ground 昀氀oor, 729.32m2 on the upper ground
昀氀oor, 728.85m2 on the 昀椀rst 昀氀oor and 993m2 of
refurbishment in the existing healthcare facility
to which this new CFU connects giving an overall
area of total of 3004m2.
Client:
HSE
Start Date:
February 2024
End Date:
June 2025
Cost Consultant:
O'Reilly Hyland Tierney
Architect:
STW Architects
Structural Engineer:
Punch Consulting Eng
Services Consultant:
Homan O’Brien
VALUE
SIZE
€20,000,000
32,335 sq. ft.
PROJECT TYPE
DURATION
PWC 4
65 Weeks