Elliott Group Brochure ROI 052022 T.2 - Flipbook - Page 48
Elliott Group | A Tradition in Construction
Cavan | Dublin | Cork | London | Birmingham
Cedral St. Conleth’s Park | Live Project
Co. Kildare
The Project includes the complete demolition
of the existing stand and dressing room block,
and the construction of a new entrance plaza,
new turnstiles, a new 3,000 seat stand, dressing
rooms, of昀椀cials changing rooms, Club Kildare
Lounge and multi-purpose rooms.
KEY FEATURES
The playing pitch will also be extended in size with
a new drainage system to Croke Park standards
along with the installation of a 昀氀ood lighting
system. Demolition of the existing covered
standbuilding, the club house, the scoreboard and
section of the front boundary wall and turnstiles.
Provision of a new entrance plaza
incorporating a ticket of昀椀ce and
turnstiles.
The construction of a new 2-storey covered
stand building, with facilities within the stand,
comprising spectator seating, players’ and
officials’ changing areas, spectators’ concourses,
circulation, toilet areas, first-aid administrative
offices, multi-purpose room, VIP/meeting
areas, hospitality and bar serving facilities;
confectionery/snack-bar facilities, stores, plant
room and associated ancillary areas.
Client:
Kildare GAA
Start Date:
March 2023
End Date:
September 2024
Structural Engineer
Donnachadh O’Brien
Architect:
COADY Architects
Cost Consultant:
Carron & Walsh
Services Consultant:
Galliao
Modi昀椀cation to external hard and soft
landscaping.
Alterations to the existing main
entrance
Replacement of some of the existing
pitch enclosures/ball netting and
an increase of the playing field
dimensions
Provision of new scoreboard and
昀氀ood lighting.
VALUE
SIZE
€16,000,000
184 Units
PROJECT TYPE
DURATION
Private
93 Weeks